Accounting Software Project

Tasks Overview Staff Overview Accounting Calendar
Tasks Details Staff Details Status Report GANTT Chart (Postscript)

This table presents a management-level overview of the project. The values are days or man-days.

No. Name Duration Work Start End Jan 2002 Feb 2002 Mar 2002 Apr 2002
 3  4  5  6  7  8  9 10 11 12 13 14 15 16 17
1 Accounting Software 90.5 180 Wed 2002-01-16 Tue 2002-04-16 v= == == == == == == == == == == == == =v  
1.1 Milestones 90.5 0 Wed 2002-01-16 Tue 2002-04-16 v= == == == == == == == == == == == == =v  
1.1.1 Projectstart 0 0 Wed 2002-01-16 Wed 2002-01-16 <>      
1.1.2 Technology Preview 0 0 Fri 2002-03-01 Fri 2002-03-01   <>    
1.1.3 Betaversion 0 0 Mon 2002-04-01 Mon 2002-04-01       <>  
1.1.4 Ship Product to customer 0 0 Tue 2002-04-16 Tue 2002-04-16       <>  
1.2 Specification 9.4 20 Wed 2002-01-16 Fri 2002-01-25 [= =]      
1.3 Manual 41.3 50 Wed 2002-01-16 Tue 2002-02-26 [= == == == == == =]    
1.4 Software Development 58.2 85 Mon 2002-01-28 Wed 2002-03-27   v= == == == == == == == =v  
1.4.1 Database coupling 11.4 20 Mon 2002-01-28 Fri 2002-02-08   [= =]      
1.4.2 Back-End Functions 18.3 30 Mon 2002-02-11 Fri 2002-03-01   [= == =]    
1.4.3 Graphical User Interface 23.1 35 Mon 2002-03-04 Wed 2002-03-27   [= == == =]  
1.5 Software testing 20 25 Wed 2002-03-27 Tue 2002-04-16       v= == == =v  
1.5.1 Alpha Test 4.9 5 Wed 2002-03-27 Mon 2002-04-01       [= =]  
1.5.2 Beta Test 15 20 Mon 2002-04-01 Tue 2002-04-16       [= == =]  