Fedora 11 Releng Team Tasks

Release Engineering: All Art Devel Docs Quality Translation Web || F10 F9
No. Name Start End Duration
1. Fedora 11 Wed 2008-11-26 Wed 2009-06-10 196.5
2. Planning Phase Wed 2008-11-26 Thu 2009-03-05 99.5
3. Start Feature Submission Wed 2008-11-26 Tue 2009-03-03 97.7
4. Naming the Release Tue 2008-12-02 Wed 2008-12-31 29.6
5. Collect Names on Wiki Tue 2008-12-02 Tue 2008-12-09 7.5
6. Board Review Tue 2008-12-09 Tue 2008-12-16 7
7. Legal Review Tue 2008-12-16 Wed 2008-12-24 8
8. Voting Wed 2008-12-24 Tue 2008-12-30 6
9. Announce Release Name Wed 2008-12-31 Wed 2008-12-31 0
10. End Feature Submission (precedes feature freeze) Tue 2009-03-03 Tue 2009-03-03 0
11. Testing Phase Tue 2009-01-13 Tue 2009-05-12 119
12. Alpha Release Tue 2009-01-13 Tue 2009-03-10 56.1
13. Create Alpha Candidate Tue 2009-01-20 Wed 2009-01-28 8
14. Alpha Freeze (depend development) Tue 2009-01-20 Tue 2009-02-03 14
15. Alpha Blocker Bug Days Mon 2009-01-26 Tue 2009-01-27 1
16. Alpha Release Meeting Wed 2009-01-28 Wed 2009-01-28 0
17. Compose Stage Sync Wed 2009-01-28 Thu 2009-02-05 8
18. Alpha Public Availability (milestone) Thu 2009-02-05 Thu 2009-02-05 0
19. Alpha Testing Thu 2009-02-05 Tue 2009-03-10 33
20. Beta Release Tue 2009-03-03 Tue 2009-04-14 42
21. Feature Freeze (depend feature submission) Tue 2009-03-03 Tue 2009-03-03 0
22. Package Walpaper for Beta Thu 2009-03-05 Fri 2009-03-06 1
23. Software String Freeze Tue 2009-03-10 Tue 2009-03-10 0
24. Create Beta Candidate Tue 2009-03-10 Wed 2009-03-25 15
25. Beta Freeze Tue 2009-03-10 Tue 2009-03-31 21
26. Beta Blocker Bug Days Mon 2009-03-16 Tue 2009-03-17 1
27. Beta Release Meeting Wed 2009-03-18 Wed 2009-03-18 0
28. Compose Stage Sync Wed 2009-03-25 Tue 2009-03-31 6
29. Beta Public Availability (milestone) Tue 2009-03-31 Tue 2009-03-31 0
30. Allow Pre-branch F12 Tue 2009-03-31 Tue 2009-03-31 0
31. Beta Testing Tue 2009-03-31 Tue 2009-04-14 14
32. Rebuild all translated packages Tue 2009-04-07 Tue 2009-04-14 7
33. Snapshot Releases Wed 2009-04-08 Fri 2009-04-10 2
34. Snapshot 1 Wed 2009-04-08 Fri 2009-04-10 2
35. Compose Stage Sync Wed 2009-04-08 Fri 2009-04-10 2
36. Public Availability Fri 2009-04-10 Fri 2009-04-10 0
37. Preview Release Tue 2009-04-07 Tue 2009-05-12 35.2
38. Final Freeze: Development Tue 2009-04-14 Tue 2009-04-14 0
39. Preview Blocker Bug Days Mon 2009-04-20 Tue 2009-04-21 1
40. Preview Release Meeting Wed 2009-04-22 Wed 2009-04-22 0
41. Compose Stage Sync (releng) Wed 2009-04-22 Tue 2009-04-28 6
42. Preview Release Public Availability (milestone) Tue 2009-04-28 Tue 2009-04-28 0
43. Preview Testing Tue 2009-04-28 Tue 2009-05-12 14
44. End of Preview Release Tue 2009-05-12 Tue 2009-05-12 0
45. Launch Phase Tue 2009-04-28 Wed 2009-06-10 42.8
46. Release Candidate Tue 2009-04-28 Wed 2009-06-10 42.8
47. GA Blocker Bug Day #1 Mon 2009-05-11 Tue 2009-05-12 0.7
48. Create & Test Preliminary Release Candidates Tue 2009-05-12 Tue 2009-06-02 20.8
49. GA Blocker Bug Day #2 Mon 2009-05-18 Tue 2009-05-19 0.7
50. GA Blocker Bug Day #3 Fri 2009-05-22 Fri 2009-05-22 0.4
51. GA Release Meeting Wed 2009-05-27 Wed 2009-05-27 0
52. Final Release Readiness Decision Tue 2009-06-02 Tue 2009-06-02 0
53. Create & Test Final Release Candidate (RC) Tue 2009-06-02 Thu 2009-06-04 2
54. Stage GA Content & Sync Mirrors Thu 2009-06-04 Tue 2009-06-09 5
55. GA Release Tue 2009-06-09 Tue 2009-06-09 0

Version 11 - Created on 2009-Jul-06 with TaskJuggler v2.4.1