Fedora 11 Quality Tasks

Quality: All Art Devel Docs RelEng Translation Web || F10 F9
No. Name Start End Duration
1. Fedora 11 Wed 2008-11-26 Wed 2009-06-10 196.5
2. Planning Phase Wed 2008-11-26 Thu 2009-03-05 99.5
3. Start Feature Submission Wed 2008-11-26 Tue 2009-03-03 97.7
4. End Feature Submission (precedes feature freeze) Tue 2009-03-03 Tue 2009-03-03 0
5. Testing Phase Tue 2009-01-13 Tue 2009-05-12 119
6. Alpha Release Tue 2009-01-13 Tue 2009-03-10 56.1
7. Alpha Blocker Bug Days Mon 2009-01-26 Tue 2009-01-27 1
8. Alpha Release Meeting Wed 2009-01-28 Wed 2009-01-28 0
9. Prepare Alpha Release Notes (1 page) Wed 2009-02-04 Thu 2009-02-05 1
10. Alpha Public Availability (milestone) Thu 2009-02-05 Thu 2009-02-05 0
11. Alpha Testing Thu 2009-02-05 Tue 2009-03-10 33
12. End of Alpha Tue 2009-03-10 Tue 2009-03-10 0
13. Beta Release Tue 2009-03-03 Tue 2009-04-14 42
14. Feature Freeze (depend feature submission) Tue 2009-03-03 Tue 2009-03-03 0
15. Beta Freeze Tue 2009-03-10 Tue 2009-03-31 21
16. Beta Blocker Bug Days Mon 2009-03-16 Tue 2009-03-17 1
17. Beta Release Meeting Wed 2009-03-18 Wed 2009-03-18 0
18. Comb Beats and Feature Pages Thu 2009-03-19 Mon 2009-03-30 11
19. Prepare Beta Release Notes (1 page) Mon 2009-03-30 Mon 2009-03-30 0.4
20. Beta Public Availability (milestone) Tue 2009-03-31 Tue 2009-03-31 0
21. Beta Testing Tue 2009-03-31 Tue 2009-04-14 14
22. End of Beta Tue 2009-04-14 Tue 2009-04-14 0
23. Preview Release Tue 2009-04-07 Tue 2009-05-12 35.2
24. Final Freeze: Development Tue 2009-04-14 Tue 2009-04-14 0
25. Preview Blocker Bug Days Mon 2009-04-20 Tue 2009-04-21 1
26. Preview Release Meeting Wed 2009-04-22 Wed 2009-04-22 0
27. Preview Release Public Availability (milestone) Tue 2009-04-28 Tue 2009-04-28 0
28. Preview Testing Tue 2009-04-28 Tue 2009-05-12 14
29. End of Preview Release Tue 2009-05-12 Tue 2009-05-12 0
30. Launch Phase Tue 2009-04-28 Wed 2009-06-10 42.8
31. Release Candidate Tue 2009-04-28 Wed 2009-06-10 42.8
32. Prepare GA Release Notes Tue 2009-04-28 Wed 2009-04-29 1
33. GA Blocker Bug Day #1 Mon 2009-05-11 Tue 2009-05-12 0.7
34. Create & Test Preliminary Release Candidates Tue 2009-05-12 Tue 2009-06-02 20.8
35. GA Blocker Bug Day #2 Mon 2009-05-18 Tue 2009-05-19 0.7
36. GA Blocker Bug Day #3 Fri 2009-05-22 Fri 2009-05-22 0.4
37. GA Release Meeting Wed 2009-05-27 Wed 2009-05-27 0
38. Final Release Readiness Decision Tue 2009-06-02 Tue 2009-06-02 0
39. Create & Test Final Release Candidate (RC) Tue 2009-06-02 Thu 2009-06-04 2
40. GA Release Tue 2009-06-09 Tue 2009-06-09 0