Combined Projects

This report has been composed out of two projects. The first project has been scheduled independently from the second project. The projects were combined while scheduling the second project.

No. Name Project ID Start End Cost Jan 2002 Feb 2002 Mar 2002 Apr 2002 May 2002 Jun 2002
 3  4  5  6  7  8  9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
1. First Project project1 (B) 2002-01-16 00:00 2002-03-26 18:00 0 v= == == == 6 10 10 7 == 5 2=v  
2. Task 1 project1 (B) 2002-01-16 00:00 2002-02-12 18:00 0 [= == == == =]  
3. Task 2 project1 (B) 2002-02-13 09:00 2002-03-05 18:00 0   [=6 10 10 4=]  
  All employees       0     6 10 10 4    
  Group 1       0   6 10 10 4      
  Joe Foo       0   3 5 5 2      
  Diana Bar       0   3 5 5 2    
4. Task 3 project1 (B) 2002-03-06 09:00 2002-03-26 18:00 0   [=3 == 5 2=]  
  All employees       0       3   5 2    
  Group 1       0     3   5 2  
  Joe Foo       0     3   5 2  
5. Second Project project2 (A) 2002-01-16 09:00 2002-04-08 14:00 13,200 v=3 5 4 == == == == 6 10 5.5 5 5 0.5=v  
6. Task 1 project2 (A) 2002-01-16 09:00 2002-01-31 18:00 3,600 [=3 5 4=]  
  All employees       3,600 3 5 4      
  Group 2       3,600 3 5 4      
  Jim Foobar       3,600 3 5 4      
7. Task 2 project2 (A) 2002-03-06 09:00 2002-03-18 14:00 5,100   [=6 10 1=]  
  All employees       5,100       6 10 1    
  Group 2       5,100     6 10 1    
  Jim Foobar       2,550     3 5 0.5    
  Greg User       2,550   3 5 0.5  
8. Task 3 project2 (A) 2002-03-18 14:00 2002-04-08 14:00 4,500   [=4.5 5 5 0.5=]  
  All employees       4,500       4.5 5 5 0.5  
  Group 2       4,500       4.5 5 5 0.5  
  Jim Foobar       4,500       4.5 5 5 0.5  

Version 1.0 - Created on 2005-12-01 15:39 with TaskJuggler v2.2.0