No. | Name | Start | End | Duration |
1. | Start Feature Submission | Wed 2009-06-10 | Wed 2009-06-10 | 0 |
2. | Create Tracker Bugs | Wed 2009-06-10 | Wed 2009-06-10 | 0 |
3. | Request Feature Status update by 2009-07-14 | Tue 2009-07-07 | Tue 2009-07-07 | 0 |
4. | Fedora 9 End of Life | Fri 2009-07-10 | Fri 2009-07-10 | 0 |
5. | Feature Page Checkpoint (all up2date) | Tue 2009-07-14 | Tue 2009-07-14 | 0 |
6. | Feature Freeze (no more features accepted) | Tue 2009-07-28 | Tue 2009-07-28 | 0 |
7. | Finalize and Package Wallpaper for Alpha | Tue 2009-07-28 | Tue 2009-08-04 | 7 |
8. | Features < 85% complete email nag | Wed 2009-07-29 | Wed 2009-07-29 | 0 |
9. | Alpha Blocker Bug Day (F12Alpha) #3 | Fri 2009-07-31 | Fri 2009-07-31 | 0 |
10. | Start Alpha Freeze | Tue 2009-08-04 | Tue 2009-08-04 | 0 |
11. | Software String Freeze | Tue 2009-08-04 | Tue 2009-08-04 | 0 |
12. | Deliver features < 85% complete to FESCo | Wed 2009-08-05 | Wed 2009-08-05 | 0 |
13. | Alpha Blocker Bug Day (F12Alpha) #4 | Fri 2009-08-07 | Fri 2009-08-07 | 0 |
14. | Alpha Blocker Bug (go/no go) | Mon 2009-08-10 | Mon 2009-08-10 | 0 |
15. | Announce: Alpha Release Readiness Meeting | Wed 2009-08-12 | Wed 2009-08-12 | 0 |
16. | Alpha Blocker Bug Day (F12Alpha) #5 | Fri 2009-08-14 | Fri 2009-08-14 | 0 |
17. | Reminder: Alpha Release Readiness Meeting | Mon 2009-08-17 | Mon 2009-08-17 | 0 |
18. | Alpha Blocker Bug (go/no go) | Mon 2009-08-17 | Mon 2009-08-17 | 0 |
19. | End Alpha Freeze | Tue 2009-08-18 | Tue 2009-08-18 | 0 |
20. | Alpha Project Wide Release Readiness Meeting | Wed 2009-08-19 | Wed 2009-08-19 | 0 |
21. | Alpha Export Control Reporting | Fri 2009-08-21 | Fri 2009-08-21 | 0 |
22. | Alpha Public Availability | Tue 2009-08-25 | Tue 2009-08-25 | 0 |
23. | Beta Blocker Bug Day (F12Beta) #1 | Fri 2009-09-11 | Fri 2009-09-11 | 0 |
24. | Beta Blocker Bug Day (F12Beta) #2 | Fri 2009-09-18 | Fri 2009-09-18 | 0 |
25. | Features < 100% email nag | Wed 2009-09-23 | Wed 2009-09-23 | 0 |
26. | Beta Blocker Bug Day (F12Beta) #3 | Fri 2009-09-25 | Fri 2009-09-25 | 0 |
27. | Final (Beta) Freeze: Development Code Complete | Tue 2009-09-29 | Tue 2009-09-29 | 0 |
28. | Deliver features < 100% to FESCo | Wed 2009-09-30 | Wed 2009-09-30 | 0 |
29. | Announce: Beta Release Readiness Meeting | Wed 2009-09-30 | Wed 2009-09-30 | 0 |
30. | Beta Blocker Day (F12Beta) #4 | Fri 2009-10-02 | Fri 2009-10-02 | 0 |
31. | Reminder: Beta Release Readiness Meeting | Mon 2009-10-05 | Mon 2009-10-05 | 0 |
32. | Beta Blocker Day (F12Beta) #5 | Fri 2009-10-09 | Fri 2009-10-09 | 0 |
33. | Beta Blocker Bug (go/no go) | Mon 2009-10-12 | Mon 2009-10-12 | 0 |
34. | Beta Project Wide Release Readiness Meeting | Wed 2009-10-14 | Wed 2009-10-14 | 0 |
35. | Beta Export Control Reporting | Fri 2009-10-16 | Fri 2009-10-16 | 0 |
36. | Beta Release Public Availability | Tue 2009-10-20 | Tue 2009-10-20 | 0 |
37. | Blocker Bug Day (F12Blocker) #1 | Fri 2009-10-23 | Fri 2009-10-23 | 0 |
38. | Blocker Bug Day (F12Blocker) #2 | Fri 2009-10-30 | Fri 2009-10-30 | 0 |
39. | Announce: Final Release Readiness Meeting | Wed 2009-11-04 | Wed 2009-11-04 | 0 |
40. | Blocker Bug Day (F12Blocker) #3 | Fri 2009-11-06 | Fri 2009-11-06 | 0 |
41. | F12 Blocker Review (go/no go) 3 PM EDT | Mon 2009-11-09 | Mon 2009-11-09 | 0 |
42. | Reminder: Final Release Readiness Meeting | Mon 2009-11-09 | Mon 2009-11-09 | 0 |
43. | F12 Project Wide Release Readiness Meeting | Wed 2009-11-11 | Wed 2009-11-11 | 0 |
44. | Final Export Control Reporting | Fri 2009-11-13 | Fri 2009-11-13 | 0 |
45. | GA Release | Tue 2009-11-17 | Tue 2009-11-17 | 0 |
Version 12 - Created on 2009-Oct-29 with TaskJuggler v2.4.1