Fedora 12 Project Management Tasks

No. Name Start End Duration
1. Start Feature Submission Wed 2009-06-10 Wed 2009-06-10 0
2. Create Tracker Bugs Wed 2009-06-10 Wed 2009-06-10 0
3. Request Feature Status update by 2009-07-14 Tue 2009-07-07 Tue 2009-07-07 0
4. Fedora 9 End of Life Fri 2009-07-10 Fri 2009-07-10 0
5. Feature Page Checkpoint (all up2date) Tue 2009-07-14 Tue 2009-07-14 0
6. Feature Freeze (no more features accepted) Tue 2009-07-28 Tue 2009-07-28 0
7. Finalize and Package Wallpaper for Alpha Tue 2009-07-28 Tue 2009-08-04 7
8. Features < 85% complete email nag Wed 2009-07-29 Wed 2009-07-29 0
9. Alpha Blocker Bug Day (F12Alpha) #3 Fri 2009-07-31 Fri 2009-07-31 0
10. Start Alpha Freeze Tue 2009-08-04 Tue 2009-08-04 0
11. Software String Freeze Tue 2009-08-04 Tue 2009-08-04 0
12. Deliver features < 85% complete to FESCo Wed 2009-08-05 Wed 2009-08-05 0
13. Alpha Blocker Bug Day (F12Alpha) #4 Fri 2009-08-07 Fri 2009-08-07 0
14. Alpha Blocker Bug (go/no go) Mon 2009-08-10 Mon 2009-08-10 0
15. Announce: Alpha Release Readiness Meeting Wed 2009-08-12 Wed 2009-08-12 0
16. Alpha Blocker Bug Day (F12Alpha) #5 Fri 2009-08-14 Fri 2009-08-14 0
17. Reminder: Alpha Release Readiness Meeting Mon 2009-08-17 Mon 2009-08-17 0
18. Alpha Blocker Bug (go/no go) Mon 2009-08-17 Mon 2009-08-17 0
19. End Alpha Freeze Tue 2009-08-18 Tue 2009-08-18 0
20. Alpha Project Wide Release Readiness Meeting Wed 2009-08-19 Wed 2009-08-19 0
21. Alpha Export Control Reporting Fri 2009-08-21 Fri 2009-08-21 0
22. Alpha Public Availability Tue 2009-08-25 Tue 2009-08-25 0
23. Beta Blocker Bug Day (F12Beta) #1 Fri 2009-09-11 Fri 2009-09-11 0
24. Beta Blocker Bug Day (F12Beta) #2 Fri 2009-09-18 Fri 2009-09-18 0
25. Features < 100% email nag Wed 2009-09-23 Wed 2009-09-23 0
26. Beta Blocker Bug Day (F12Beta) #3 Fri 2009-09-25 Fri 2009-09-25 0
27. Final (Beta) Freeze: Development Code Complete Tue 2009-09-29 Tue 2009-09-29 0
28. Deliver features < 100% to FESCo Wed 2009-09-30 Wed 2009-09-30 0
29. Announce: Beta Release Readiness Meeting Wed 2009-09-30 Wed 2009-09-30 0
30. Beta Blocker Day (F12Beta) #4 Fri 2009-10-02 Fri 2009-10-02 0
31. Reminder: Beta Release Readiness Meeting Mon 2009-10-05 Mon 2009-10-05 0
32. Beta Blocker Day (F12Beta) #5 Fri 2009-10-09 Fri 2009-10-09 0
33. Beta Blocker Bug (go/no go) Mon 2009-10-12 Mon 2009-10-12 0
34. Beta Project Wide Release Readiness Meeting Wed 2009-10-14 Wed 2009-10-14 0
35. Beta Export Control Reporting Fri 2009-10-16 Fri 2009-10-16 0
36. Beta Release Public Availability Tue 2009-10-20 Tue 2009-10-20 0
37. Blocker Bug Day (F12Blocker) #1 Fri 2009-10-23 Fri 2009-10-23 0
38. Blocker Bug Day (F12Blocker) #2 Fri 2009-10-30 Fri 2009-10-30 0
39. Announce: Final Release Readiness Meeting Wed 2009-11-04 Wed 2009-11-04 0
40. Blocker Bug Day (F12Blocker) #3 Fri 2009-11-06 Fri 2009-11-06 0
41. F12 Blocker Review (go/no go) 3 PM EDT Mon 2009-11-09 Mon 2009-11-09 0
42. Reminder: Final Release Readiness Meeting Mon 2009-11-09 Mon 2009-11-09 0
43. F12 Project Wide Release Readiness Meeting Wed 2009-11-11 Wed 2009-11-11 0
44. Final Export Control Reporting Fri 2009-11-13 Fri 2009-11-13 0
45. GA Release Tue 2009-11-17 Tue 2009-11-17 0

Version 12 - Created on 2009-Oct-29 with TaskJuggler v2.4.1