Fedora 12 Quality Tasks

Quality: Key All Design Devel Docs Marketing RelEng Translation Web || F11 F10
No. Name Start End Duration
1. Fedora 12 Wed 2009-06-10 Tue 2009-12-15 188.8
2. Planning Phase Wed 2009-06-10 Tue 2009-07-28 48.7
3. Feature Submission and Acceptance Wed 2009-06-10 Tue 2009-07-28 48.7
4. Development Phase Wed 2009-06-10 Tue 2009-08-04 55.7
5. Alpha Blocker Bug Day (F12Alpha) #1 Fri 2009-07-17 Fri 2009-07-17 0
6. Alpha Blocker Bug Day (F12Alpha) #2 Fri 2009-07-24 Fri 2009-07-24 0
7. Testing Phase Tue 2009-07-28 Wed 2009-11-04 99
8. Alpha Release Tue 2009-07-28 Wed 2009-09-30 64
9. Feature Freeze (no more features accepted) Tue 2009-07-28 Tue 2009-07-28 0
10. Test 'Test Compose' (boot media testing) Wed 2009-07-29 Wed 2009-08-05 7
11. Alpha Blocker Bug Day (F12Alpha) #3 Fri 2009-07-31 Fri 2009-07-31 0
12. Start Alpha Freeze Tue 2009-08-04 Tue 2009-08-04 0
13. Alpha Blocker Bug Day (F12Alpha) #4 Fri 2009-08-07 Fri 2009-08-07 0
14. Alpha Blocker Bug (go/no go) Mon 2009-08-10 Mon 2009-08-10 0
15. Alpha Blocker Bug Day (F12Alpha) #5 Fri 2009-08-14 Fri 2009-08-14 0
16. Alpha Blocker Bug (go/no go) Mon 2009-08-17 Mon 2009-08-17 0
17. Test Alpha Candidate Mon 2009-08-17 Thu 2009-08-20 3
18. End Alpha Freeze Tue 2009-08-18 Tue 2009-08-18 0
19. Alpha Project Wide Release Readiness Meeting Wed 2009-08-19 Wed 2009-08-19 0
20. Alpha Release Notes Wed 2009-08-19 Tue 2009-08-25 6
21. Start Alpha Beat and Feature Page Review Wed 2009-08-19 Wed 2009-08-19 0
22. Comb Beats and Feature Pages for Alpha Wed 2009-08-19 Mon 2009-08-24 5
23. Prepare Alpha Release Notes (1 page) Mon 2009-08-24 Mon 2009-08-24 0
24. Alpha Public Availability Tue 2009-08-25 Tue 2009-08-25 0
25. Alpha Testing Tue 2009-08-25 Tue 2009-09-29 35
26. Beta Blocker Bug Day (F12Beta) #1 Fri 2009-09-11 Fri 2009-09-11 0
27. Pre-Beta Rawhide Install Test Plan Wed 2009-09-16 Wed 2009-09-23 7
28. Beta Blocker Bug Day (F12Beta) #2 Fri 2009-09-18 Fri 2009-09-18 0
29. Test 'Test Compose' (boot media testing) Wed 2009-09-23 Wed 2009-09-30 7
30. Beta Blocker Bug Day (F12Beta) #3 Fri 2009-09-25 Fri 2009-09-25 0
31. End of Alpha Testing Tue 2009-09-29 Tue 2009-09-29 0
32. Beta Release Mon 2009-08-24 Wed 2009-11-04 72
33. Final (Beta) Freeze: Development Code Complete Tue 2009-09-29 Tue 2009-09-29 0
34. Beta Blocker Day (F12Beta) #4 Fri 2009-10-02 Fri 2009-10-02 0
35. Test Beta Candidate Thu 2009-10-08 Thu 2009-10-15 7
36. Beta Blocker Day (F12Beta) #5 Fri 2009-10-09 Fri 2009-10-09 0
37. Beta Blocker Bug (go/no go) Mon 2009-10-12 Mon 2009-10-12 0
38. Beta Project Wide Release Readiness Meeting Wed 2009-10-14 Wed 2009-10-14 0
39. Beta Release Public Availability Tue 2009-10-20 Tue 2009-10-20 0
40. Beta Testing Tue 2009-10-20 Mon 2009-11-02 13
41. Blocker Bug Day (F12Blocker) #1 Fri 2009-10-23 Fri 2009-10-23 0
42. Pre-RC Rawhide Install Test Plan Wed 2009-10-28 Wed 2009-11-04 7
43. Blocker Bug Day (F12Blocker) #2 Fri 2009-10-30 Fri 2009-10-30 0
44. End of Beta Testing Mon 2009-11-02 Mon 2009-11-02 0
45. Launch Phase Tue 2009-10-20 Tue 2009-12-15 56
46. Release Candidate Tue 2009-10-20 Wed 2009-11-18 29
47. Final Release Notes Tue 2009-10-20 Tue 2009-11-17 28
48. Prepare GA Release Notes Tue 2009-10-20 Tue 2009-10-20 0
49. Test RC Wed 2009-11-04 Wed 2009-11-11 7
50. Blocker Bug Day (F12Blocker) #3 Fri 2009-11-06 Fri 2009-11-06 0
51. F12 Blocker Review (go/no go) 3 PM EDT Mon 2009-11-09 Mon 2009-11-09 0
52. F12 Project Wide Release Readiness Meeting Wed 2009-11-11 Wed 2009-11-11 0
53. GA Release Tue 2009-11-17 Tue 2009-11-17 0

Version 12 - Created on 2009-Oct-29 with TaskJuggler v2.4.1